A1 Complete Builders were awarded contracts to convert this old barn and build 2 further extensions by our existing client.
The barn has been stripped leaving the stone walls in situ, block built up gable end and a Glulam beam fitted with timber frame dwarf walls built to increase height and enable two bedrooms to first floor. Construct walls and fit wooden staircase. Also benefiting with underfloor heating run by a ground source system, three 50 meter trenches with coil pipes connecting to a manifold.
The first extension is one storey timber frame again with a Glulam beam fitted supporting rafters. Construction of a bedroom ensuite with family bathroom and lounge.
Underfloor heating installed again all run by ground source heating. The second extension is a new kitchen being built later this year.
Duration of time on site – 12 weeks