Project 2015, Mount Wise Newquay. [Timber frame Kitchen Extension]
Our client is the head vet from The Animal Hospital where we completed an operating theatre in 2014. A1 was Instructed to undertake this project and the demolition of a shed cleared the way for the kitchen extension to be built. The frame is built on stilts supporting the front of the building and is timber frame from the ground up.
A high end specification using 140mm timber framing with earth wool insulation and an air tight Pro Clima Intello Plus check barrier/membrane, fitted to the inside with 40mm wood fibre laid with a batten service void and then finished with 12 mm Ply under 12.5 mm plaster board.
External is fitted with Bitroc boards over total area and stainless steel mesh lath before rendering over. Most materials used is Eco Friendly and local sourced timber. The general idea is to make this not only air tight but a breathable construction giving our clients a large warm family kitchen extension. The flooring used is Egger Waterproof Boarding with a ceramic tile finish.
The Roof is a flat roof with a River Pebble finish laid over a E.D.P.M Membrane over 18 mm Deck. A Douglas Fir decking built alongside to finish. The kitchen supplied by Howdens and fitted by A1 Complete Builders. All electrics and plumbing in-house and over seen by A1.
Duration of time on site 11 weeks