A1 Complete Builders have been instructed to undertake extensive external works to an existing clients property in Mousehole. Our Clients parking area is showing signs of slippage and moving.
J.L.A Engineering consultants have designed 3 concrete retaining walls with steel mesh and bars built in to cavities with concrete c35 infill. Around 300 tons of top soil/concrete must be removed in small loads as access is difficult and around 250 tons to be bought back in mainly 805 permeable stone, 60 tons of concrete and some 3,500 concrete blocks.
Once all walls are built and new ramp formed the area will be blocked paved over.
Read a testimonial from the owners here
Duration of time on site 5 months